Multiple Choice
It took 44 hours of analysis to complete the first phase,but the second phase was done in 42 hours.If this learning rate continues,then the 8th analysis should take a mere:
A) 36 hours and 26 minutes,give or take.
B) 37 hours and 36 minutes,give or take.
C) 38 hours and 16 minutes,give or take.
D) 39 hours and 6 minutes,give or take.
Correct Answer:

Verified
Correct Answer:
Verified