Multiple Choice
Contingency money is:
A) Not formally in the project budget,but held in a separate company account for all projects.
B) Added to the project's budget following the identification of all project costs.
C) The first line item in any project budget at an amount dictated by company policy.
D) Not in the project's budget,but calculated and set aside once the project budget is completed.
Correct Answer:

Verified
Correct Answer:
Verified
Q21: The charge that is most likely a
Q22: What are three benefits to the use
Q23: An activity with a learning rate of
Q24: The project management research in brief titled
Q25: Explain the difference between normal and expedited
Q27: It began as a simple macro that
Q28: Once most of the design work is
Q29: If it takes 40 hours to complete
Q30: A budget contingency of $1 million on
Q31: It took 44 hours of analysis to