Hammock activities allow:
A) Project managers to streamline the linkage and sequencing between activities.
B) Project workers to effectively skip nonessential activities without compromising project quality.
C) The project team to better disaggregate the overall project network into logical summaries.
D) The project manager to identify float more quickly and leverage it more successfully for the overall success of the project.