Use the Values in the Table to Calculate Activity Durations

Question 74

Essay

Use the values in the table to calculate activity durations and variances for the project.What is the project deadline such that there is a 75% chance it is completed on time?
 Activity  Activity time  Standard  deviation  Predecessor A123B82 AC91 AD51 BE120 BF100CG72CH93E,GI152D,GT82HK113IL72 J, K\begin{array}{|l|l|l|l|}\hline \text { Activity } & \text { Activity time } & \begin{array}{l}\text { Standard } \\\text { deviation }\end{array} & \text { Predecessor } \\\hline \mathrm{A} & 12 & 3 & \\\hline \mathrm{B} & 8 & 2 & \mathrm{~A} \\\hline \mathrm{C} & 9 & 1 & \mathrm{~A} \\\hline \mathrm{D} & 5 & 1 & \mathrm{~B} \\\hline \mathrm{E} & 12 & 0 & \mathrm{~B} \\\hline \mathrm{F} & 10 & 0 & \mathrm{C} \\\hline \mathrm{G} & 7 & 2 & \mathrm{C} \\\hline \mathrm{H} & 9 & 3 & \mathrm{E}, \mathrm{G} \\\hline \mathrm{I} & 15 & 2 & \mathrm{D}, \mathrm{G} \\\hline \mathrm{T} & 8 & 2 & \mathrm{H} \\\hline \mathrm{K} & 11 & 3 & \mathrm{I} \\\hline \mathrm{L} & 7 & 2 & \mathrm{~J}, \mathrm{~K} \\\hline\end{array}

Correct Answer:

verifed

Verified

The critical path is ACGIKL and has an e...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions