    The Length of Time Expected to Complete an Activity Assuming
Solved

The Length of Time Expected to Complete an Activity Assuming

Question 62

Question 62

Multiple Choice

The length of time expected to complete an activity assuming that its development proceeds normally is called the:


A) Optimistic duration.
B) Pessimistic duration.
C) Most likely duration.
D) Normal duration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q57: There's an old saying,"The job is not

Q58: Phoebe B.Beebee is constructing a canal

Q59: A gentleman farmer maniacally works on

Q60: A project's duration can be reduced by:<br>A)Shortening

Q61: Use the values in the table

Q63: An activity has an optimistic time estimate

Q64: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network

Q65: A backward pass is performed when it

Q66: Which technique would accelerate the completion of

Q67: What is the slack time for

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines