Multiple Choice
An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?
A) 3.33
B) 6.66
C) 9.99
D) 11.11
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q58: Phoebe B.Beebee is constructing a canal
Q59: A gentleman farmer maniacally works on
Q60: A project's duration can be reduced by:<br>A)Shortening
Q61: Use the values in the table
Q62: The length of time expected to complete
Q64: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q65: A backward pass is performed when it
Q66: Which technique would accelerate the completion of
Q67: What is the slack time for
Q68: One approach to reducing project length would