Multiple Choice
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities E and F can be represented by a hammock activity.What are the duration and the early start time associated with this hammock activity?
A) 13,36
B) 7,0
C) 13,7
D) 7,14
Correct Answer:

Verified
Correct Answer:
Verified