menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    The Amount of Time an Activity May Be Delayed from Its
Solved

The Amount of Time an Activity May Be Delayed from Its

Question 3

Question 3

Multiple Choice

The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:


A) Delay.
B) Float.
C) Late start.
D) Late finish.

Correct Answer:

verifed

Verified

Related Questions

Q2: Use the information in the table

Q4: Use the values in the table

Q5: A gentleman farmer maniacally works on

Q6: Use the information in the table

Q7: Based on the activity network pictured,what is

Q8: An activity has an optimistic time estimate

Q9: A merge activity has two or more

Q10: The PERT technique assumes that durations are

Q11: Compute early and late start and finish

Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines