A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project is completed in 31 days?
A) 0.055
B) 0.092
C) 0.125
D) 0.187