Solved

Use the Information in the Table (All Times Are in Days)to

Question 36

Multiple Choice

Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000.  Normal Minimum Crash Cost ActivityTimeTime ($/day)   Predecessor A106$70B63$40C22BD42$60CE64$80AF85$90D,E\begin{array}{|l|l|l|l|l|} \hline&\text { Normal }&\text {Minimum}&\text { Crash Cost }\\ \text {Activity}&\text {Time}&\text {Time}&\text { (\$/day) }& \text { Predecessor }\\\hline \mathrm{A}& 10 & 6 & \$ 70 & -- \\ \hline \mathrm{B} & 6 & 3 & \$ 40 & -- \\\hline\mathrm{C} & 2 & 2 & - &\mathrm{B } \\\hline\mathrm{D} & 4 & 2 & \$ 60 &\mathrm{ C } \\\hline \mathrm{E} & 6 & 4 & \$ 80 &\mathrm{ A } \\\hline\mathrm{F} & 8 & 5 & \$ 90 & \mathrm{D},\mathrm{ E }\\\hline \end{array}


A) $400
B) $420
C) $440
D) $460

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions