Multiple Choice
Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000.
A) $400
B) $420
C) $440
D) $460
Correct Answer:

Verified
Correct Answer:
Verified