Solved

The Heir to the Throne Was Due 60 Days from Now

Question 38

Essay

The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.The seven activities,their normal and expedited times (in days)and costs appear in the table.Just to be on the safe side,he decided to bring the project in at 53 days in case the delivery was a week early.Tell him what the least expensive 53-day project is;which activities should be reduced in duration,by how many days,and at the total cost,so he can roll up the sleeves on his "World's Greatest Dad" sweatshirt,and get to work.
 Normal  Crash  Normal  Crash  Activity  time  time  Cost  Cast  Predecesar A55001100B18159002300AC12925003000AD97500650BE151230005000BF121040005000C,DG201536004800E,F\begin{array} { | l | l | l | l | l | l |} \hline & \text { Normal } & \text { Crash } & \text { Normal } & \text { Crash } & \\\text { Activity } & \text { time } & \text { time } & \text { Cost } & \text { Cast } & \text { Predecesar } \\\hline\mathrm { A }& 5 & 500 & 1100 & \\\hline \mathrm { B } & 18 & 15 & 900 & 2300 &\mathrm { A } \\\hline \mathrm { C } & 12 & 9 & 2500 & 3000 & \mathrm { A } \\\hline \mathrm { D } & 9 & 7 & 500 & 650 &\mathrm { B } \\\hline \mathrm { E } & 15 & 12 & 3000 & 5000 &\mathrm { B } \\\hline \mathrm { F } & 12 & 10 & 4000 & 5000 & \mathrm { C } , \mathrm { D } \\\hline \mathrm {G}&20&15&3600&4800& \mathrm {E,F}\\\hline\end{array}

Correct Answer:

verifed

Verified

The project before any expediting takes ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions