A Project Has the Activity Duration and Cost Information Indicated
Question 57
Question 57
Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 40 days? Activity ABCDEFGHJ Predecessor −AABCEDAH Normal Time 812153978126 Normal Cost $12,000$18,000$22,000$9,000$15,000$5,000$13,000$20,000$45,000 Crash Time 599255684 Crash Cost $22,000$32,000$62,000$18,000$35,000$8,000$23,000$32,000$56,000
A) $172,000 B) $218,000 C) $192,000 D) $159,000
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge