Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 60

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 33 weeks?  Activity  Narmal  time  Crash  time  Narmal  Cust  Crash  Cast  Predecessar  A 85$1,0002,000B641,5002,000 A C851,8002,300 A B1291,0001,800 BE14119501,450 BF971,5001,900C,DG752,3002,800E,F\begin{array} { | l | l | l | l | l | l } \hline \text { Activity } & \begin{array} { l } \text { Narmal } \\\text { time }\end{array} & \begin{array} { l } \text { Crash } \\\text { time }\end{array} & \begin{array} { l } \text { Narmal } \\\text { Cust }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cast }\end{array} & \text { Predecessar } \\\hline \text { A } & 8 & 5 & \$1 , 000 & 2,000 & \\\hline B & 6 & 4 & 1,500 & 2,000 & \text { A } \\\hline \mathrm { C } & 8 & 5 & 1,800 & 2,300 & \text { A } \\\hline \mathrm { B } & 12 & 9 & 1,000 & 1,800 & \mathrm {~B} \\\hline \mathrm { E } & 14 & 11 & 950 & 1,450 & \mathrm {~B} \\\hline \mathrm { F } & 9 & 7 & 1,500 & 1,900 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 7 & 5 & 2,300 & 2,800 & \mathrm { E } , \mathrm { F } \\\hline\end{array}


A) $11,250
B) $11,500
C) $12,250
D) $12,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions