Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $4,000 per week for every week the project exceeds 37 weeks.What is the lowest total cost for completing this project?
A) $172,000
B) $184,000
C) $187,000
D) $192,500
Correct Answer:

Verified
Correct Answer:
Verified