Consider the Project Described by the Table Where All Durations

Question 84

Essay

Consider the project described by the table where all durations are in days and the costs in dollars.What is the minimum cost of completing this project in 150 days?
 Normal  Minimum Normal  Activity Predecessor Time  Time  Cost  Crash Cost A15128001,100BA30222,5004,100CA453721,00033,000DC201715,00022,000ED543,0003,300FB10713,00015,500GF302541,00046,000HJ,E504530,00037,500JF252020,00025,000KG35336,5007,200LK403316,50019,400ML151314,40018,600NK302623,50027,500PH201515,25023,500QN,P555,0005,000\begin{array}{|l|l|l|l|l|l|}\hline&&\text { Normal } & \text { Minimum } & \text {Normal }\\ \text { Activity} & \text { Predecessor } & \text {Time } & \text { Time } & \text { Cost } & \text { Crash Cost }\\ \hline\mathrm{A} & 15 & 12 & 800 & 1,100 & \\\hline\mathrm{B} & \mathrm{A} & 30 & 22 & 2,500 & 4,100 \\\hline \mathrm{C} & \mathrm{A} & 45 & 37 & 21,000 & 33,000 \\\hline \mathrm{D} & \mathrm{C} & 20 & 17 & 15,000 & 22,000 \\\hline\mathrm{E} & \mathrm{D} & 5 & 4 & 3,000 & 3,300 \\\hline\mathrm{F} & \mathrm{B} & 10 & 7 & 13,000 & 15,500 \\\hline \mathrm{G} & \mathrm{F} & 30 & 25 & 41,000 & 46,000 \\\hline \mathrm{H} & \mathrm{J}, \mathrm{E} & 50 & 45 & 30,000 & 37,500 \\\hline \mathrm{J} & \mathrm{F} & 25 & 20 & 20,000 & 25,000 \\\hline\mathrm{K} & \mathrm{G} & 35 & 33 & 6,500 & 7,200 \\\hline\mathrm{L} & \mathrm{K} & 40 & 33 & 16,500 & 19,400 \\\hline\mathrm{M} &\mathrm{L} & 15 & 13 & 14,400 & 18,600 \\\hline \mathrm{N} & \mathrm{K} & 30 & 26 & 23,500 & 27,500 \\\hline\mathrm{P} & \mathrm{H} & 20 & 15 & 15,250 & 23,500 \\\hline\mathrm{Q} & \mathrm{N}, \mathrm{P} & 5 & 5 & 5,000 & 5,000\\\hline \end{array}

Correct Answer:

verifed

Verified

The crash cost per day has been added to...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions