A Project Has the Activity Duration and Cost Information Indicated
Question 69
Question 69
Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project as quickly as possible? Activity A B C DEFGHJ Predecessor −− A A B C EDAH Normal Time 812153978126 Normal Cost $12,000$18,000$22,000$9,000$15,000$5,000$13,000$20,000$45,000 Crash Time 599255684 Crash Cost $22,000$32,000$62,000$18,000$35,000$8,000$23,000$32,000$56,000
A) $244,000 B) $255,600 C) $258,333 D) $262,000
Correct Answer:
Verified