Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 69

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project as quickly as possible?  Activity  Predecessor  Normal  Time  Normal  Cost  Crash Time  Crash Cost  A 8$12,0005$22,000B A 12$18,0009$32,000 C  A 15$22,0009$62,000DB3$9,0002$18,000E C 9$15,0005$35,000FE7$5,0005$8,000GD8$13,0006$23,000HA12$20,0008$32,000JH6$45,0004$56,000\begin{array}{|l|l|l|l|l|l|}\hline \text { Activity } & \text { Predecessor } & \begin{array}{l}\text { Normal } \\\text { Time }\end{array} & \begin{array}{l}\text { Normal } \\\text { Cost }\end{array} & \text { Crash Time } & \text { Crash Cost } \\\hline \text { A } &--& 8 & \$ 12,000 & 5 & \$ 22,000 \\\hline \mathrm{B} & \text { A } & 12 & \$ 18,000 & 9 & \$ 32,000 \\\hline \text { C } & \text { A } & 15 & \$ 22,000 & 9 & \$ 62,000 \\\hline \mathrm{D} & \mathrm{B} & 3 & \$ 9,000 & 2& \$ 18,000 \\\hline \mathbf{E} & \text { C } & 9 & \$ 15,000 & 5 & \$ 35,000 \\\hline \mathrm{F} & \mathrm{E} & 7 & \$ 5,000 & 5 & \$ 8,000 \\\hline \mathrm{G} & \mathrm{D} & 8 & \$ 13,000 & 6 & \$ 23,000 \\\hline \mathrm{H} & \mathrm{A} & 12 & \$ 20,000 & 8 & \$ 32,000 \\\hline \mathrm{J} & \mathrm{H} & 6 & \$ 45,000 & 4 & \$ 56,000 \\\hline\end{array}



A) $244,000
B) $255,600
C) $258,333
D) $262,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions