Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 67

Essay

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 33 weeks?
 Activity  Narmal  time  Crash  time  Normal  Cost  Crash  Cost  Predecessor  A 85$,0002,000B641,5002,000 A C851,8002,300 A B1291,0001,800 BE14119501,450 BF971,5001,900C,DG752,3002,800E,F\begin{array} { | l | l | l | l | l | l| } \hline \text { Activity } & \begin{array} { l } \text { Narmal } \\\text { time }\end{array} & \begin{array} { l } \text { Crash } \\\text { time }\end{array} & \begin{array} { l } \text { Normal } \\\text { Cost }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cost }\end{array} & \text { Predecessor } \\\hline \text { A } & 8 & 5 & \$ , 000 & 2,000 & \\\hline B & 6 & 4 & 1,500 & 2,000 & \text { A } \\\hline \mathrm { C } & 8 & 5 & 1,800 & 2,300 & \text { A } \\\hline \mathrm { B } & 12 & 9 & 1,000 & 1,800 & \mathrm {~B} \\\hline \mathrm { E } & 14 & 11 & 950 & 1,450 & \mathrm {~B} \\\hline \mathrm { F } & 9 & 7 & 1,500 & 1,900 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 7 & 5 & 2,300 & 2,800 & \mathrm { E } , \mathrm { F } \\\hline\end{array}

Correct Answer:

verifed

Verified

$12,250 is the least expensive 33 week p...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions