The sprint portion of the Agile Project Management process is targeted to last:
A) 10 plus or minus 2 weeks.
B) 7 plus or minus 1.5 weeks.
C) 5 plus or minus 1.5 weeks.
D) 2.5 plus or minus 1.5 weeks.