Multiple Choice
All of these happen during the sprint phase EXCEPT:
A) Technical issues are forwarded to the product owner.
B) Scope clarification.
C) Sprint goal modification.
D) Scope renegotiation.
Correct Answer:

Verified
Correct Answer:
Verified