Multiple Choice
XYZ project organization has one workstation that is capable of generating the drawings that their clients study before accepting XYZ's bid.XYZ is currently in the midst of three proposal projects and knows exactly when it will need to use the workstation.All other work to be done,both before and after the workstation is used,is scheduled such that it flows to the workstation and keeps it busy.Resources used after this step are less critical;so while the subsequent work and resources are important,they aren't viewed with the same reverence as the workstation.This is an example of:
A) Identifying a constraint.
B) Elevating a constraint.
C) Subordinating a system.
D) Exploiting a constraint.
Correct Answer:

Verified
Correct Answer:
Verified
Q80: Agile project management is well-suited for the
Q81: In Agile Project Management,a sprint backlog is
Q82: What are the formal steps to apply
Q83: The critical chain is usually the same
Q84: A project consists of four activities
Q86: List any three criticisms of critical chain
Q87: Describe three or more of the keys
Q88: What is the waterfall planning process and
Q89: Wayne and Garth are engaged in XP
Q90: Organizations recognize that moving to Agile methods