Solved

A Project Consists of Four Activities with Information as Shown

Question 84

Multiple Choice

A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project's duration?  Standard  Activity  Predecessor  Length  Deviation  A 102 B  A 123 C  A 162 D B,C143\begin{array}{|l|l|l|l|}\hline&&&\text { Standard }\\ \text { Activity } & \text { Predecessor } & \text { Length } & \begin{array}{l}\text { Deviation }\end{array} \\\hline \text { A } & - & 10 & 2 \\\hline \text { B } & \text { A } & 12 & 3 \\\hline \text { C } & \text { A } & 16 & 2 \\\hline \text { D } & \text {B,C} & 14 & 3\\\hline \end{array}


A) 6.2
B) 4.1
C) 2.8
D) 5.1

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions