Multiple Choice
Which statement about critical chain methodology is BEST?
A) Activity durations estimated at a 50% level of successful completion are shorter than those estimated at a 90% level of successful completion.
B) Aggregated activity durations at a 90% level of successful completion are shorter than aggregated activity durations at a 50% level of successful completion.
C) The total safety buffer for aggregated activity durations is smaller than the sum of safety buffers for individual activity durations at any likely level estimate.
D) None of these statements is correct.
Correct Answer:

Verified
Correct Answer:
Verified
Q31: The legal department is needed to review
Q32: A feeder buffer is a buffer that
Q33: What are the five steps behind the
Q34: A project consists of four consecutive
Q35: A project is represented by the
Q37: A product backlog:<br>A)Shows remaining work in the
Q38: The first step in TOC methodology is
Q39: When choosing the most viable solution to
Q40: A key to successful project management is
Q41: A project is represented by the