Solved

Which Statement About Critical Chain Methodology Is BEST

Question 36

Multiple Choice

Which statement about critical chain methodology is BEST?


A) Activity durations estimated at a 50% level of successful completion are shorter than those estimated at a 90% level of successful completion.
B) Aggregated activity durations at a 90% level of successful completion are shorter than aggregated activity durations at a 50% level of successful completion.
C) The total safety buffer for aggregated activity durations is smaller than the sum of safety buffers for individual activity durations at any likely level estimate.
D) None of these statements is correct.

Correct Answer:

verifed

Verified

Unlock this answer now