A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology?
A) 13.5
B) 22.5
C) 11.25
D) 9.0
Correct Answer:

Verified
Correct Answer:
Verified
Q36: Which statement about critical chain methodology is
Q37: A product backlog:<br>A)Shows remaining work in the
Q38: The first step in TOC methodology is
Q39: When choosing the most viable solution to
Q40: A key to successful project management is
Q42: Wayne and Garth are engaged in XP
Q43: Which of the following statement is BEST?<br>A)The
Q44: Agile project management features a logical series
Q45: A project is represented by the
Q46: A project that consists of six