Multiple Choice
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology?
A) 22.5
B) 24.75
C) 27.0
D) 33.75
Correct Answer:

Verified
Correct Answer:
Verified
Q53: A system-wide constraint is called a:<br>A)Rope.<br>B)Resource.<br>C)Drum.<br>D)Chain.
Q55: What are the key elements of extreme
Q56: Which statement about critical chain project management
Q57: Picture yourself as a project manager intent
Q59: A project is represented by the
Q60: In order to resolve a resource conflict,it
Q61: Which adjective is most appropriate for Agile
Q62: A project consists of four activities
Q63: Alexander Demetrius Dickson,ADD to his friends,has three
Q74: The one element that Agile shares with