Picture Yourself as a Project Manager Intent on Bringing CCPM

Question 57

Essay

Picture yourself as a project manager intent on bringing CCPM to your organization that has historically used classic critical path project management.How would you convince your project team to develop 50% estimates for their project contributions rather than the 90% estimates they have used since they started with the company?