Multiple Choice
A resource loading chart displays:
A) The amount of time needed as a function of resource limits.
B) The amount of resources required as a function of time.
C) The amount of time needed as a function of money.
D) The amount of resources needed as a function of money.
Correct Answer:

Verified
Correct Answer:
Verified