Consider the Project That Is Neatly Summarized in This Table

Question 23

Multiple Choice

Consider the project that is neatly summarized in this table.What are the top two priority activities when using the smallest duration leveling heuristic?  Activity  Duration  Predecessors  Workers Required  A 23B4 A 4C6 A 2D7 B5E9C,D,E2\begin{array} { | l | l | l | l | } \hline\text { Activity } & \text { Duration } & \text { Predecessors } & \text { Workers Required } \\\hline \text { A } & 2 & - & 3 \\\hline B & 4 & \text { A } & 4 \\\hline \mathrm { C } & 6 & \text { A } & 2 \\\hline \mathrm { D } & 7 & \mathrm {~B} & 5 \\\hline \mathrm { E } & 9 & \mathrm { C } , \mathrm { D } , \mathrm { E } & 2 \\\hline\end{array}


A) B and C
B) A and B
C) C and E
D) A and E

Correct Answer: