Multiple Choice
Splitting activities refers to:
A) Assigning the work to two or more workers.
B) Assigning the work to two or more days.
C) Starting an activity,interrupting it to use a resource elsewhere,and then returning to work on the activity.
D) Breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor.
Correct Answer:

Verified
Correct Answer:
Verified