A Project Consists of Six Activities (All Times Are Given

Question 52

Essay

A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
 Activity  Duration (days)  Activity Cost  Predecessor K10140L864K,MM1296N6120MP14168LQ12144N\begin{array}{|l|l|l|l|}\hline \text { Activity } & \text { Duration (days) } & \text { Activity Cost } & \text { Predecessor } \\\hline\mathrm{K} & 10 & 140 & \\\hline\mathrm{L} & 8 & 64 & \mathrm{K}, \mathrm{M} \\\hline \mathrm{M} & 12 & 96 & \\\hline \mathrm{N} & 6 & 120 &\mathrm{M} \\\hline \mathrm{P} & 14 & 168 & \mathrm{L} \\\hline\mathrm{Q} & 12 & 144 & \mathrm{N} \\\hline \end{array}

Correct Answer:

verifed

Verified

Highest resource usage occurs during day...