-The Project Represented by This Resource Load Chart Has a Maximum

Question 95

Multiple Choice

  -The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are: A) Activity A B) Activities B and C C) Activities D and E D) Activity E and F
-The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:


A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F