Multiple Choice
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number?
A) Activity A
B) Activity B
C) Activity C
D) Activity D
Correct Answer:

Verified
Correct Answer:
Verified