A Project Consisting of Six Activities Is Shown in the Table.The

Question 76

Multiple Choice

A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:  Activity  Duration (days)   Activity Cost  Predecessor K10140L864 K,MM1296N6120MP14168 LQ12144 N\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Duration (days) } & \text { Activity Cost } & \text { Predecessor } \\\hline \mathrm { K } & 10 & 140 & \\\hline \mathrm { L } & 8 & 64 & \mathrm {~K} , \mathrm { M } \\\hline \mathrm { M } & 12 & 96 & \\\hline \mathrm { N } & 6 & 120 & \mathrm { M } \\\hline \mathrm { P } & 14 & 168 & \mathrm {~L} \\\hline \mathrm { Q } & 12 & 144 & \mathrm {~N} \\\hline\end{array}


A) On days 19 through 20 for an early start schedule.
B) On days 17 through 20 for a late start schedule.
C) On days 13 through 18 for an early start schedule.
D) On days 21 through 22 for a late start schedule.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions