Solved

Use the Project Described in the Table to Determine the Total

Question 65

Multiple Choice

Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day) to this project.  Activity  Duration  Predecessor  A 5 days B4 days  A C5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l| } \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \text { A } & 5 \text { days } & - \\\hline B & 4 \text { days } & \text { A } \\\hline C& 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & B \\\hline E & 6 \text { days } & C , D \\\hline F & 6 \text { days } &E \\\hline\end{array}


A) 4 hours
B) 2 hours
C) 8 hours
D) 6 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions