Create a Resource Loading Table and Perform Resource Leveling on the Project

Question 61

Essay

Create a resource loading table and perform resource leveling on the project composed of the activities in this table.Activities listed in the table are measured in the number of eight-hour days.The maximum amount of time used per day is 16 hours.
 Activity  Time  Predecessor  A 6B1C2 A, BD4E1C,DFEEG6EH4 FJ4 FK3G,HL5J, KM5L\begin{array} { | l | l | l |} \hline\text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 6 & - \\\hline B & 1 & - \\ \hline \mathrm { C } & 2 & \mathrm {~A} , \mathrm {~B} \\\hline \mathrm { D } & 4 & - \\\hline \mathrm { E } & 1 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & \mathrm { E } & \mathrm { E } \\\hline \mathrm {G } & 6 & \mathrm { E } \\\hline \mathrm { H } & 4 & \mathrm {~F} \\\hline \mathrm { J } & 4 & \mathrm {~F} \\\hline \mathrm { K } & 3 & \mathbf { G } , \mathrm { H } \\\hline \mathrm { L } & 5 & \mathrm {J} , \mathrm {~K} \\\hline \mathrm { M } & \mathbf { 5 } & \mathrm { L } \\\hline\end{array}

Correct Answer:

verifed

Verified

The initial resource loading table with ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions