A Project Consists of Eleven Activities (All Times Are Given

Question 2

Multiple Choice

A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity H start under a leveled project with the four worker limitation?  Activity  Activity time  Workers Needed  Predecessor  A 101 B 42 C 73 A D41 A  E 82 B F 93 C,E  G 131D H 142 E, G  J 133 FK101H,JL52 K\begin{array}{|l|l|l|l|}\hline \text { Activity } & \text { Activity time } & \text { Workers Needed } & \text { Predecessor } \\\hline \text { A } & 10 & 1 & \\\hline \text { B } & 4 & 2 & \\\hline \text { C } & 7 & 3 & \text { A } \\\hline \mathrm{D} & 4 & 1 & \text { A } \\\hline \text { E } & 8 & 2 & \mathrm{~B} \\\hline \text { F } & 9 & 3 & \text { C,E } \\\hline \text { G } & 13 & 1 & \mathrm{D} \\\hline \text { H } & 14 & 2 & \text { E, G } \\\hline \text { J } & 13 & 3 & \mathrm{~F} \\\hline \mathrm{K} & 10 & 1 & \mathrm{H}, \mathrm{J} \\\hline \mathrm{L} & 5 & 2 & \mathrm{~K} \\\hline\end{array}



A) Day 27
B) Day 28
C) Day 29
D) Day 30

Correct Answer:

verifed

Verified

Related Questions