Multiple Choice
It is possible to measure:
A) Only positive deviations from the schedule baseline with a tracking Gantt chart.
B) Only negative deviations from the schedule baseline with a tracking Gantt chart.
C) Both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
D) Both positive and negative deviations from the budget with the tracking Gantt chart.
Correct Answer:

Verified
Correct Answer:
Verified
Q75: A tracking Gantt chart:<br>A)Monitors costs and budget
Q76: The Project Implementation Profile includes this critical
Q77: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the S-curve
Q78: Use this earned schedule table to
Q79: The flow of the Earned Value Management
Q81: Use the information in the table
Q82: How does a tracking Gantt chart's appearance
Q83: The budget variance is calculated as:<br>A)Earned value
Q84: Take the factors considered by earned value
Q85: The earned value to date divided by