menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 13: Project Evaluation and Control
  5. Question
    The Budget Variance Is Calculated As
Solved

The Budget Variance Is Calculated As

Question 83

Question 83

Multiple Choice

The budget variance is calculated as:


A) Earned value minus planned value.
B) Planned value minus actual cost.
C) Earned value minus actual cost.
D) Cost minus planned value.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q78: Use this earned schedule table to

Q79: The flow of the Earned Value Management

Q80: It is possible to measure:<br>A)Only positive deviations

Q81: Use the information in the table

Q82: How does a tracking Gantt chart's appearance

Q84: Take the factors considered by earned value

Q85: The earned value to date divided by

Q86: The closer to completion a project gets,the

Q87: What are the problems with milestones as

Q88: You are the new consultant to the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines