Multiple Choice
Take the factors considered by earned value analysis and subtract those considered by tracking Gantt charts.The factor(s) you have remaining are:
A) Cost.
B) Cost and schedule.
C) Schedule and performance.
D) Performance.
Correct Answer:

Verified
Correct Answer:
Verified