Use the Earned Value Table to Determine the Estimated Cost

Question 73

Multiple Choice

Use the earned value table to determine the estimated cost to completion given the indicated state of the project.  Activity 5101520253035 Plan % Complete  A 8503501,200100% B 400125525100%C1,2756501,925100%D28004,5003507,65095%E6804001,08075%F1258751,00080%30012001,50045% Monthly Plan 8507501,4003,4505,1801,1752,07514,880 Monthly Act 9006501,3503,8754,7808502,000\begin{array}{|l|l|l|l|l|l|l|l|l|l|}\hline \text { Activity } & 5 & 10 & 15 & 20 & 25 & 30 & 35 & \text { Plan } & \% \text { Complete } \\\hline \text { A } & 850 & 350 & & & & & & 1,200 & 100 \% \\\hline \text { B } & & 400 & 125 & & & & & 525 & 100 \% \\\hline \text {C} & & & 1,275 & 650 & & & & 1,925 & 100 \% \\\hline \text {D} & & & & 2800 & 4,500 & 350 & & 7,650 & 95 \% \\\hline \text {E} & & & & & 680 & 400 & & 1,080 & 75 \% \\\hline \text {F} & & & & & & 125 & 875 & 1,000 & 80 \% \\\hline \text {G } & & & & & & 300 & 1200 & 1,500 & 45 \% \\\hline \text { Monthly Plan } & 850 & 750 & 1,400 & 3,450 & 5,180 & 1,175 & 2,075 & 14,880 & \\ \hline \text { Monthly Act } & 900 & 650 & 1,350 & 3,875&4,780 & 850 & 2,000 & & \\\hline\end{array}


A) $15,966
B) $16,173
C) $18,164
D) $17,441

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions