Multiple Choice
Duration (weeks)
-At the end of week 25,this project has cost $79,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars.
A) 1.11
B) 0.82
C) 0.94
D) 0.90
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Planned value is:<br>A)The total budget for the
Q5: What are drawbacks to a pure S-curve
Q6: What is a tracking Gantt chart and
Q7: If significant deviations from the project plan
Q8: A project manager can calculate the projected
Q10: Briefly describe the important differences between Earned
Q11: Positive variance on an S-curve is not
Q12: Briefly describe any seven critical success factors
Q13: What is the significance of the 0/100
Q14: Use the data to calculate the