Use the Data to Calculate the Schedule Performance Index for the Project

Question 14

Multiple Choice

Use the data to calculate the schedule performance index for the project for the end of week 20.The earned value as of the end of week 20 is indicated in the table.All amounts are in thousands of dollars. Duration (weeks)
510152025%Cormp Conceptual desiern 106100% Craphics desigrl 1264100% Copyright 45660% Barmples 42100% Toolirg 69450% Production 261420% Total 1018222624 Currulative 10285076100\begin{array} { | l | l | l | l | l | l | l | } \hline & 5 & 10 & 15 & 20 & 25 & \%\mathrm { Cormp } \\\hline \text { Conceptual desiern } & 10 & 6 & & & & 100 \% \\\hline \text { Craphics desigrl } & & 12 & 6 & 4 & & 100 \% \\\hline \text { Copyright } & & & 4 & 5 & 6 & 60 \% \\\hline \text { Barmples } & & & 4 & 2 & & 100 \% \\\hline \text { Toolirg } & & & 6 & 9 & 4 & 50 \% \\\hline \text { Production } & & & 2 & 6 & 14 & 20 \% \\\hline \text { Total } & 10 & 18 & 22 & 26 & 24 & \\\hline \text { Currulative } & 10 & 28 & 50 & 76 & 100 & \\\hline\end{array}


A) 1.14
B) 0.88
C) 0.94
D) 0.81

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions