Use the Earned Value Table for Project Makeready to Determine
Question 99
Question 99
Multiple Choice
Use the earned value table for Project Makeready to determine the schedule variance. Activity Install fixtures Refinish floors Replace doors Complete tiling Install back door Landscaping Monthly Plan Monthly Act 7325325550142505508005502185350435550282751,2005651,4751,100∣1,650358751,440425550422252003501,100491,7653505,250 plan 57563562580%1,10070%5508 Complete 100%100%100%25%
A) -$1,896 B) -$1,096 C) -$800 D) -$206