Duration (Weeks) -Use the Data to Calculate the Earned Value for the |

Question 104

Multiple Choice

Duration (weeks)
510152025%Cormp Conceptual desiern 106100% Craphics desigrl 1264100% Copyright 456100% Barmples 4270% Toolirg 69450% Production 261420% Total 1018222624 Currulative 10285076100\begin{array} { | l | l | l | l | l | l | l | } \hline & 5 & 10 & 15 & 20 & 25 &\%\mathrm { Cormp } \\\hline \text { Conceptual desiern } & 10 & 6 & & & & 100 \% \\\hline \text { Craphics desigrl } & & 12 & 6 & 4 & & 100 \% \\\hline \text { Copyright } & & & 4 & 5 & 6 & 100 \% \\\hline \text { Barmples } & & & 4 & 2 & & 70 \% \\\hline \text { Toolirg } & & & 6 & 9 & 4 & 50 \% \\\hline \text { Production } & & & 2 & 6 & 14 & 20 \% \\\hline \text { Total } & 10 & 18 & 22 & 26 & 24 & \\\hline \text { Currulative } & 10 & 28 & 50 & 76 & 100 & \\\hline\end{array}
-Use the data to calculate the earned value for the project.All amounts are in thousands of dollars.


A) $65,500
B) $69,550
C) $71,100
D) $76,125

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions