Multiple Choice
A project will have more than one IRR if:
A) the IRR is positive.
B) the IRR is negative.
C) the NPV is zero.
D) the cash flow pattern exhibits more than one sign change.
E) the cash flow pattern exhibits exactly one sign changE.