Multiple Choice
The elements that cause problems with the use of the IRR in projects that are mutually exclusive are:
A) the discount rate and scale problems.
B) timing and scale problems.
C) the discount rate and timing problems.
D) scale and reversing flow problems.
E) timing and reversing flow problems.
Correct Answer:

Verified
Correct Answer:
Verified
Q51: A project will produce cash inflows of
Q53: The internal rate of return tends to
Q54: The profitability index is closely related to:<br>A)
Q55: The problem of multiple IRRs can occur
Q57: An investment project has the cash flow
Q58: Given that the net present value (NPV)
Q59: Discuss how frequently publicly traded firms use
Q60: The payback period rule:<br>A) discounts cash flows.<br>B)
Q61: You are considering two independent projects with
Q98: All else equal,the payback period for a