Multiple Choice
What is the standard time (ST) for this task if the employee worked at a twenty-five percent faster pace than the average and an allowance of twenty percent of the workday is used?
A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds
Correct Answer:

Verified
Correct Answer:
Verified