Multiple Choice
Which of the following is not a form of risk reduction in project management?
A) Backup systems
B) Outsourcing components of the project
C) Frequent monitoring of project activities
D) Expand the project scope to reduce external dependencies
E) Improving communications
Correct Answer:

Verified
Correct Answer:
Verified