Solved

Given the Portion of the Network Shown Above,based on the Activity

Question 21

Multiple Choice

  Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23? A)  18 B)  17 C)  13 D)  12 E)  10 Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?


A) 18
B) 17
C) 13
D) 12
E) 10

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions