Multiple Choice
Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?
A) 18
B) 17
C) 13
D) 12
E) 10
Correct Answer:

Verified
Correct Answer:
Verified