Multiple Choice
What is the estimated standard deviation of the duration for activity E?
A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q15: The project management strategy of injecting additional
Q16: The life cycle of a project includes
Q21: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2512/.jpg" alt=" Given the portion
Q36: Consecutive activities on the same path have
Q41: Which of the following would probably not
Q43: The task of identifying risks should involve
Q58: The standard deviation of a project duration
Q70: The critical path has zero path slack
Q96: The principal advantage a Gantt chart has
Q129: Activity D has an optimistic duration of