Multiple Choice
In the probabilistic approach to precedence network analysis,the duration estimate annotated "tm" for any activity is the:
A) mean duration.
B) median duration.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.
Correct Answer:

Verified
Correct Answer:
Verified